Contact Us Our Attorneys Frequently Asked Questions Directions to our Location Back to Home
   
Statute of Repose Bars Suit Against Builder

The Court of Appeals of Maryland held that Maryland’s ten year statute of repose precluded a suit for construction defects from being filed against a contractor twelve years after completion of an eleven-story building, even though the defects were not discovered during the first ten years the building was occupied.

Hagerstown Elderly Associates Limited Partnership is the owner of a public housing facility in Hagerstown, Maryland. The building was completed in December of 1983. In 1995, during a severe storm, a portion of an exterior wall of the eleven-story building fell to the ground. On October 16, 1996, the partnership filed suit in the Circuit Court for Washington County against Hagerstown Elderly Building Associates (HEBA), the contractor that erected the building, and Seaboard Surety Company (Seaboard), the surety on the performance bond filed by HEBA. The owner sued to recover the expense of repairing the building.

The Circuit Court for Washington County granted summary judgment to HEBA on the grounds that the action against the builder was barred by the ten-year "statute of repose" codified in Maryland Code, § 5-108 (b) of the Courts and Judicial Proceedings Article.

A statute of repose extinguishes a cause of action after a fixed period of time, usually measured from the delivery of the product or the completion of the work, regardless of when the defect became apparent or when cause of action accrued. By contrast, the time constraint imposed by a "statute of limitations" generally does not begin run until after the cause of action accrues.

Section 5-108 (b) imposes a ten-year period of repose on actions against any architect, professional engineer, or contractor. It provides:

"Except as provided by this section, a cause of action for damages does not accrue and a person may not seek contribution or indemnity from any architect, professional engineer, or contractor for damages incurred when wrongful death, personal injury, or injury to real or personal property, resulting from the defective and unsafe conditions of an improvement to real property, occurs more than 10 years after the date the entire improvement first became available for its intended use."

In this case, the building first became available for its intended use in December, 1983, when the final inspection was completed, a certificate of occupancy was issued, permission to occupy all units was issued, and the first occupancy by a tenant occurred. Accordingly, the Circuit Court ruled that any claim against the contractor more than 10 years after December 1983 was precluded by Section 5-108(b).

On appeal, the partnership argued that Section 5-108(b) did not apply to its action for breach of contract and breach of warranty, but applied only to tort actions. The Court of Appeals rejected that argument and held that the Section 5-108(a) was applicable not only to tort actions asserting claims for negligence and strict liability, but to breach of contract and breach of warranty claims as well.

The Court of Appeals explained that the statute of repose was "intended to protect architects, engineers, contractors, and others involved in the construction industry from being hauled into court by reason of latent defects that did not become manifest until years after the completion of construction.... That protection would be fragile, indeed, if it depended on how a plaintiff chooses to frame and plead its cause of action." The Court of Appeals upheld the lower court’s summary judgment in favor of the contractor.

The Circuit Court also granted summary judgment to Seaboard, the bonding company, on the grounds that the action against it was barred by the 12 year statute of limitations codified in Courts and Judicial Proceedings Article, § 5-102(a)(2), concluding that the suit was filed twelve years and six days after that cause of action accrued, i.e., after the final payment was due. Both parties agreed that the 12 year statute of limitations applied, but they disagreed about when the final payment was "due" under the construction contract. That date was important because it started the 12 year period running. Seaboard argued that final payment was due October 10, 1984, and that the suit filed on October 16, 1996, was six days too late. The Court of Appeals, however, found that pursuant to the construction contract, the final payment was not due until the final loan closing, which occurred on November 1, 1984, and that suit had therefore been timely filed against Seaboard. The lower court’s summary judgment in favor of Seaboard was reversed, and the case was remanded for further proceedings. 

Hagerstown Elderly Associates Limited Partnership, et al. v. Hagerstown Elderly Building Associates, et al., ___ Md ____ , 2002, No. 29, September Term, 2001, decided March 12, 2002.


[Return to Real Estate Update]

 

 

 
Practice Areas | Real Estate Law Resource Center | Family Law Resource Center | Our Attorneys | FAQ | Firm Information
Newsletters | Directions | Contact Us | Site Map | Home

Copyright © Warfield & Darrah, P.C., Severna Park, Maryland. All rights reserved.
Web Site by Consultwebs.com, Specializing In Webs For Lawyers